|Mossad and Israeli Special Forces infiltrate Iran for a secret operation Details of the daring ground operation yet unknown | Kuwaiti defence forces mistakenly shoot down three USAF F 15E Strike Eagle aircraft | All Six Pilots Parachute Safely and are in hospitals for Checks | F 15E is a powerful warjet, has two pilots, one to Fly and the other as a Weapons Officer | Iran meanwhile has widened its missile strikes whiie the US Air Force and Navy have intensified Bombing of Iran | US Def Sec Hegseth says There Are No Timelines BUT IRAN WILL NOT HAVE NUCLEAR CAPABILITY | And that ‘War Will Not Be Endless’ | Trump asks Iranians to ‘Rise up and Take Over Your Government’ | Iran says No Negotiations With US | Trump Confirms Iran’s Supreme Islamic Leader ‘evil’ Ali Khamenei killed in targeted missile strikes | Many Iranian military and Islamic leaders also dead | US and Israel launched the biggest ever military strikes in history to decimate Iran’s top leadership | There are no reported of boots on ground | About 200 USAF and Navy jets are hammering Iran’s political and military targets without stop | The missiles are precision | Care is taken to avoid cities and civilians | It’s War | US and Israel attack Iran | Trump says Will Not Allow to Have Nuclear Bomb | Iran Retaliates with Missiles across Gulf and Jordan | But Not Oman | US Bases in UAE, Saudi Arabia, Bahrain, Qatar, Kuwait Hit | Trump asks Iranians to Remove Evil Regime and Take Over | Trump says US Will Annihilate Iranian Navy | Free Exchange of Missiles and Drones | Iranian Foreign Minister Calls For Stopping Attacks and Then Talks | Iran under Internet Blockade | UK PM says Our Planes in Sky for Defensive Operations | Terror Anywhere Threatens Peace Everywhere: PM Narendra Modi while Addressing Israeli Knesset | PM Modi in Israel, Prime Minister Netanyahu receives him with warm hugs | India clears Grand Mother of All Defence Deals Ever - For $ 40 Billion | Dassault Rafales, Airbus Helicopters, Boeing P 8I, Sikorsky MH 60R, Newer Technology Weapons and Drones Cleared | Modi, Macron announce India-France Strategic Partnership And India-France Year of Innovation | India Finally Decides to Buy 114 Rafale Fighters | Big, Bold Decision by Modi Government | Virtual paralysis in MoD Ends, 35 Years After VP Singh’s Lies Over Bofors | Prime Minister Modi Initiates Many Other Reforms on Defence | Congratulations Mr Modi | Nuclear Talks with US a Good Start, says Iran | Oman will continue to Mediate and host the Talks | India’s Agni-3 Nuclear IRBM Test Successful | India, US Trade Pact May be signed in March, says Commerce and Industry Minister Piyush Goyal | US asks Russia and China for a Fresh Nuclear Treaty | India’s Oil Imports from Russia lowest at $2.7 billion in 38 months | RIL buys 2 million barrels of Venezuelan Oil | India fully paid the Committed $120 million to Iran for Chabahar Port development | Project though is uncertain due to US pressure | Police cannot arrest an accused simply to Ask Questions, rules the Supreme Court of India | Adani Defence, Leonardo Aerospace in partnership to make advanced Helicopters in India | Leonardo Aerospace collaborates with Adani Defence to manufacture advanced Helicopters in India | The two companies announced an MoU to set up a ‘fully integrated Helicopter Manufacturing Ecosystem in India’ | ‘Any Attack Will be an All Out War Against Us,’ says Iran | India votes Against a Human Rights motion Censuring Iran in UN | Indian Woman Preeti Unhale Lives for 25 Years With Donor Heart ♥
AERO INDIA 2025DEFENCE INDUSTRY

Delivering TEJAS MK-1A our Primary Aim, not Countering Criticism: HAL CMD D K Sunil

By R Anil Kumar

  • The IAF chief A P Singh had pointed out that the delays in delivering the TEJAS MK-1A jets have been a major source of discontent within the Air Force. He noted that HAL had failed to operate in a “mission mode,” which he deemed necessary for timely delivery

  • In response to the criticism, HAL Chairman DK Sunil acknowledged the delays but attributed them to supply chain disruptions, particularly related to engine manufacturing issues with General Electric. He assured that efforts were underway to resolve these problems and confirmed that deliveries would begin once the engines arrive

Bengaluru. The recent remarks by Air Chief Marshal Amar Preet Singh at Aero India 2025 have spotlighted significant concerns regarding Hindustan Aeronautics Limited’s (HAL) progress on the Light Combat Aircraft (LCA) TEJAS MK-1A. During the event, Singh openly had criticised HAL for failing to deliver on promised timelines, stating that not a single aircraft was ready despite assurances that 11 would be completed by February 2025.

Dr. D K Sunil, Chairman and Managing Director, Hindustan Aeronautics Limited.

Air Chief Marshal A P Singh expressed strong dissatisfaction with HAL’s performance, particularly concerning the delays in delivering the TEJAS MK-1A fighter jets.

He had stated, “I have no confidence in HAL,” highlighting a critical situation for the IAF as it faces declining fighter squadron strength, currently at 31 against a sanctioned strength of 42.

Singh emphasised that HAL had failed to deliver promised aircraft, noting that he was assured that 11 TEJAS MK-1As would be ready by February, but none were available.

His comments were particularly pointed, emphasising a lack of confidence in HAL’s operational readiness and mission focus.

Chief of Air Staff AP Singh had expressed his frustration, saying, “I am just not confident of HAL, which is a very wrong thing to happen”. He highlighted that HAL’s presentation of aircraft labelled as MK-1A did not meet the expected specifications, asserting that mere software updates or cosmetic changes do not qualify as genuine upgrades.

The IAF chief pointed out that the delays in delivering the TEJAS MK-1A jets have been a major source of discontent within the Air Force. He noted that HAL had failed to operate in a “mission mode,” which he deemed necessary for timely delivery.

In response to the criticism, HAL Chairman DK Sunil acknowledged the delays but attributed them to supply chain disruptions, particularly related to engine manufacturing issues with General Electric. He assured that efforts were underway to resolve these problems and confirmed that deliveries would begin once the engines arrive.

The HAL Chief assured that once engines are supplied, production would accelerate. Sunil expressed commitment to resolving these issues and emphasised HAL’s dedication to supporting the IAF’s requirements.

“Our focus is not on getting into a debate on this. I’d rather channelise the energy of my teams on delivering the aircraft. ‘Tu tu main main se kuch nahin hoga’ (squabbling will not serve any purpose),” DK Sunil said.

“We have built three MK-1A fighters and flew them with ‘Category B’ (reserve) engines at the airshow. The aircraft are fully ready in hardware, equipped with a more capable radar, the jammer is there, the electronic warfare suite is there, it has a new mission computer and a smart multi-function display. All the stuff that we had promised is there and fully integrated. Now we are in the final stages of firing the indigenous Astra beyond-visual-range air-to-air missile. We will do it in the next 15 days,” the HAL chief when contacted, said.

Singh had urged for a “drastic change” in HAL’s approach to align efforts and improve outcomes. He stated, “Something must change. Some drastic change. This needs a magic wand so everything gets aligned”.

The backdrop of these comments includes ongoing challenges in India’s defence indigenization efforts, particularly concerning the TEJAS program. The IAF has ordered 83 TEJAS MK-1A aircraft to bolster its fighter fleet, which has been shrinking due to aging aircraft. The urgency for these deliveries is underscored by the current operational needs of the Air Force, which is struggling with a reduced number of fighter squadrons.

HAL has made some progress with prototypes and public displays at Aero India 2025, the IAF chief’s remarks reflect deep-seated frustrations over unmet expectations and highlight the critical need for improvements in production timelines and operational efficiency within India’s defence manufacturing sector.